ErichHahn completed the modernization of a process section at the SOCAR Kulevi oil terminal on the Black Sea coast of Georgia.

Upgraded HPS-90 pumping stations in explosion-proof design were installed at the site. The stations are designed for pumping viscous and solidifying petroleum products. Submerged heat exchangers were installed in parallel, piping was reworked, and the units were automated.

The scope of work included development of operating and detailed working documentation, supply of equipment, installation, commissioning, personnel training and start-up.

The equipment was delivered in February 2025. The project expands the presence of ErichHahn solutions in the terminal infrastructure of the Caspian–Black Sea corridor.